How to order a subscription
1. Statement on the accession treaty
Your M&E designer will ask us for the initial information – that is, the connection approval – which will be provided within two weeks, and will then draw up the plans. You can then apply for planning permission.
2. Application for membership
Once a planning permission has been granted, you can apply for a connection by completing a connection application form.
Fill in order form3. Subscription Agreement
We will be in touch with you to go through the details of the contract. We will sign the subscription contract. The subscription will be invoiced when the contract is signed, and the payment term is one month.
4. Making a connection
A water connection is being installed. Water consumption during the works will be charged in accordance with the price list. The cost of opening the valve will also be charged at the same time.
5. Fitting a water meter
Order the installation of a water meter by completing the meter installation form.
Fill in the form